BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: April 15, 2014
TO: Honorable Chairman and Members of the Board
FROM: Sunil Harman
SUBJECT: [Airport] Bob Sikes Airport Parking Lot Project
DEPARTMENT: Airport
BCC DISTRICT: All
STATEMENT OF ISSUE: The Board of County Commissioners is requested to approve
Change Order No. 1 with Birkshire Johnston, LLC (Okaloosa County Contract Number C13-
2070-AP).
BACKGROUND: This change order proposes to add 63 calendar days to the construction
contract to align the construction schedule with the concurrent construction schedule of the
privately funded Emerald Coast Aviation Terminal Development project.
OPTIONS: Approve, Reject or Table
RECOMMENDATIONS: Approve Change Order No. 1 with Birkshire Johnston, LLC to add
63 calendar days to the construction contract.
RECOMMENDED BY:
APPROVED BY:
Ernie Padgett, County Administrator