READ ALONGSIDE THE SOURCE
Okaloosa County BOCC — April 27, 2013 — March 19 Project Update — reading text
Part 1 of 1. These parts divide the reading text for browsing; they are not the source document's page numbers.
Machine-extracted text — 170-March 19 Project Update.pdf
Machine-extracted OCR text · Review label: Machine produced / unreviewed
Compare this copy with the preserved source. Review labels describe the recorded status of this file; they do not guarantee that the text is error-free. Spacing and line breaks are retained, with long lines wrapped to fit the screen.
Photos courtesy of Matt
Trammell, Taylor Engineering
• Over 600,000 cy of sand placed
• Beach elevation increased over 5 feet
• Shoreline advanced on average over 180 feet
• 23 Marine turtles safely netted and relocated
• Total project cost under $8 million
authorized by the BOCC
Photo courtesy of Matt Trammell,
Taylor Engineering
Okaloosa Island and Western Destin Dune
Vegetation and Sand Fencing Project
Tentative Construction Schedule
• Mobilization ..............................................March 30 and 31
• Delivery of Fence Material ......................April 1
• Fence Installation ....................................April 2 to April 15
• Plant Installation Western Destin ...........April 15 to April 30
• Plant Installation Okaloosa Island ..........May 1 to May 21,