ADVERTISEMENT OF COMPLETION
(Contractor)
(Address)
give notice of completion of
(Project)
and sets as the date of final settlement. All persons and firms
should file all claims for payment to the below address prior to the settlement date:
Okaloosa Board of County Commissioners, (Owner)
c/o Polyengineering, Inc.
P. O. Box 841
Shalimar, FL 32579
By: (Name)
(Title)
Leg: (Publication Dates)
Repair & Paint
Countryview & Bluewater Tanks (2014) 01700-5 Job No. 41-459
Packet Pg. 247
CONTRACTOR'S RELEASE OF LIENS
STATE OF:
COUNTY OF:
Before me, the undersigned Notary Public in and for the said County and State personally
appeared , representing the Contractor, , who being duly
sworn according to law deposes and says that all labor, materials, and outstanding claims and
indebtedness of whatever nature arising out of the performance of the Contract with Board of
County Commissioners, Okaloosa County, FL, the Owner, for ,
Contract No. have been paid in full and that for the final payment in the amount of
$ , the Contractor releases and discharges the Owner and his authorized
representatives from any liens or claims of any nature because of or arising from this contract
and/or its performance, which it has had, has or may have in the future.
By:
Sworn to and subscribed
before me this day of .
(Notary Public)
My Commission expires
Repair & Paint
Countryview & Bluewater Tanks (2014) 01700-6 Job No. 41-459
Packet Pg. 248
[Date]
Polyengineering, Inc
PO Box 841
Shalimar, FL 32579
Reference: [Project Name]
Dear [Engineer] ,
As required in the contract specifications, upon expiration of our current Certificate of Insurance,
an additional copy will forwarded to you for your records.
[Contractors Name] will maintain our insurance coverage in excess of two (2) years from
completion.
If you have questions or require additional information, please do not hesitate to call.
END OF SECTION 01700
Repair & Paint
Countryview & Bluewater Tanks (2014) 01700-7 Job No. 41-459
Packet Pg. 249
SECTION 01711
CLEANUP
1.1 GENERAL
This section covers the general cleaning which the Contractor shall be required to
perform both during construction and before final acceptance of the project unless
otherwise shown on the Drawings or specified elsewhere in these Specifications.
1.2 HAZARD CONTROL
A. The Contractor shall prevent accumulation of wastes which create hazardous
conditions.
B. Burning or burying rubbish and waste materials on the site shall not be allowed.
C. Disposal of volatile wastes into sanitary or storm sewers shall not be allowed.
1.3 DISPOSAL OF SURPLUS MATERIALS
A. Unless otherwise shown on the Drawings, specified or directed, the Contractor
shall dispose of all surplus excavated materials and equipment from demolition,
legally off the site, and shall provide his own suitable, off-site spoil area, or on a
site designated by the Owner.
1.4 FINAL CLEANING
The Contractor shall:
A. Remove from the site all plant, material, tools and equipment belonging to him,
and leave the site with an appearance acceptable to the Engineer.
B. The Contractor shall thoroughly clean all equipment materials installed by him
and shall deliver over such materials and equipment in a bright, clean, polished
and new-appearing condition.
C. Restoration of Landscape Damage. Any landscape feature scarred or damaged by
the Contractor's equipment or operations shall be restored as nearly as possible to
its original condition at the Contractor's expense. The Engineer will decide what
method of restoration shall be used.
Repair & Paint
Countryview & Bluewater Tanks (2014) 01711-1 Job No. 41-459
Packet Pg. 250
D. Post-Construction Cleanup or Obliteration. The Contractor shall obliterate all
signs of temporary construction facilities such as haul roads, work areas,
structures, stockpiles of excess or waste materials, or any other vestiges of
construction, as directed by the Engineer.
END OF SECTION 01711
Repair & Paint
Countryview & Bluewater Tanks (2014) 01711-2 Job No. 41-459
Packet Pg. 251
SECTION 01740
WARRANTIES AND BONDS
PART 1 - GENERAL
1.1 PROJECT MAINTENANCE AND WARRANTY
A. Maintain and keep in good repair the improvements covered by these Drawings
and Specifications during the life of the Contract.
B. Indemnify the Owner against any repairs which may become necessary to any
part of the work performed and to items of equipment and systems procured for or
furnished under this Contract, arising from defective workmanship or materials
used therein, for a period of five (5) years after acceptance from the final date of
final resolution of the Owner accepting work.
C. The Contractor shall not be obligated to make replacements which become
necessary because of ordinary wear and tear, or as a result of improper operation
or maintenance, or as a result of improper work or damage by another Contractor
or the Owner, or to perform any work which is normally performed by a
maintenance crew during operation.
D. In the event of multiple failures of major consequences prior to the expiration of
the five-year warranty described above, the affected unit shall be disassembled,
inspected, and modified or replaced as necessary to prevent further occurrences.
All related components which may have been damaged or rendered non-
serviceable as a consequence of the failure shall be replaced. As used herein,
multiple failures shall be interpreted to mean two (2) or more successive failures
of the same kind in the same item or failures of the same kind in two (2) or more
items. Major failures may include, but are not limited to, cracked or broken
housings, piping, or vessels, excessive deflections, bent or broken shafts, broken
or chipped gear teeth, premature bearing failure, excessive wear, or excessive
leakage around seals. Failures which are directly and clearly traceable to operator
abuse, such as operations in conflict with published operating procedures, or
improper maintenance, such as substitution of unauthorized replacement parts,
use of incorrect lubricants or chemicals, flagrant over- or under-lubrication, and
using maintenance procedures not conforming with published maintenance
instructions, shall be exempted from the scope of the one-year warranty. Should
multiple failures occur in a given time, all products of the same size and type shall
be disassembled, inspected, modified or replaced, as necessary and rewarranted
for one year.
E. The Contractor shall, at his own expense, furnish all labor, materials, tools and
equipment required and shall make such repairs and removals or shall perform
Repair & Paint
Countryview & Bluewater Tanks (2014) 01740-1 Job No. 41-459
Packet Pg. 252
such work or reconstruction as may be made necessary by any structural or
functional defect or failure resulting from neglect, faulty workmanship or faulty
materials, in any part of the Work performed by him. Such repair shall also
include refilling of trenches, excavations or embankments which show settlement
or erosion after backfilling or placement.
F. Except as noted on the Drawings or as specified, all structures such as
embankments and fences shall be returned to their original condition prior to the
completion of the Contract. Any and all damage to any facility not designated for
removal, resulting from the Contractor's operations, shall be promptly repaired by
the Contractor at no cost to the Owner.
G. In the event the Contractor fails to proceed to remedy the defects of which he has
been notified within fifteen (15) days of the date of such notice, the Owner
reserves the right to cause the required materials to be procured and the work to
be done, as described in the Drawings and Specifications, and to hold the
Contractor and the sureties on his bond liable for the cost and expense thereof.
I. Notice to Contractor for repairs and reconstruction will be made in the form of a
registered letter addressed to the Contractor at his home office.
J. Neither the foregoing paragraphs nor any provision in the Contract Documents,
nor any special guarantee time limit implies any limitation of the Contractor's
liability with the law of the place of construction.
END OF SECTION 01740
Repair & Paint
Countryview & Bluewater Tanks (2014) 01740-2 Job No. 41-459
Packet Pg. 253
SECTION 09870
REPAIRING AND REPAINTING WATER TANKS
PART 1 - GENERAL
1.1 SECTION INCLUDES
Blasting, cleaning, repairing, and painting the Countryview and Bluewater Water Storage
Tanks.
1.2 RELATED SECTIONS
Section 01300 - Submittals
1.3 PROJECT CONDITIONS
A General Arrangement Drawings and Site Plans (See Appendix) of the two tanks to be