Repair & Paint
Countryview & Bluewater Tanks 00100-1 Job No. 41-459
Packet Pg. 133
All references shall include (but not be limited to):
• Name of Project
• Project Location
• Owner Name, Address and Telephone Number
• Owner Email (if available)
• Owner Contact Name
• Project Engineer Firm, Address and Telephone Number
• Engineer Email (if available)
• Engineer Contact Name
3.03 Reference Scope of Work for Exterior Surfaces (10 tanks minimum for each):
• Full containment system with a bonnet, minimum SSPC Guide 6 Class 3 including air
filtration, as specified in Section 09870.
• Exterior abrasive blast cleaned to SSPC-SP 10 Near White Finish with recyclable
steel grit.
• Application of an organic, zinc-rich urethane primer, epoxy and/or urethane
intermediate and fluoropolymer urethane or polyurethane finish to exterior surface.
3.04 Reference Scope of Work for Interior Surfaces (10 tanks minimum for each):
• Abrasive blast cleaned with recyclable steel grit and using adequately sized air
filtration, as specified in Section 09870.
• Installation of a moisture cured, urethane organic, zinc-rich primer.
• Installation of 100% solids by volume, heated plural component applied, interior
lining system
• High voltage discontinuity testing of thick film interior lining systems.
3.05 The successful low bidder will be required to acquire a county business license before the
contract will be awarded.
ARTICLE 4 - EXAMINATION OF BIDDING DOCUMENTS, OTHER RELATED
DATA, AND SITE.
4.01 Subsurface and Physical Conditions
A. Reference is made to the Supplementary Conditions for the identification of:
1. Those reports of explorations and tests of subsurface conditions at or
contiguous to the Site, if any, that ENGINEER has used in preparing the
Bidding Documents.
2. Those drawings of physical conditions in or relating to existing surface
and subsurface structures at or contiguous to the Site (except Underground
Repair & Paint
Countryview & Bluewater Tanks 00100-2 Job No. 41-459
Packet Pg. 134
Facilities) that ENGINEER has used in preparing the Bidding Documents.
B. Copies of reports and drawings referenced in paragraph 4.01.A will be made
available by OWNER to any Bidder on request. Those reports and drawings are not part of the
Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to
rely as provided in paragraph 4.02 of the General Conditions has been identified and established
in paragraph 4.02 of the Supplementary Conditions. Bidder is responsible for any interpretation
or conclusion Bidder draws from any “technical data” or any other data, interpretations, opinions
or information contained in such reports or shown or indicated in such drawings.
4.02 Underground Facilities
A. Information and data shown or indicated in the Bidding Documents with respect to
existing Underground Facilities at or contiguous to the Site is based upon information and data
furnished to OWNER and ENGINEER by owners of such Underground Facilities, including
OWNER, or others. ENGINEER assumes no responsibility for the accuracy or completeness of
the information furnished by said owners.
4.03 Hazardous Environmental Condition
A. The Supplementary Conditions identify those reports and drawings relating to a
Hazardous Environmental Condition identified at the Site, if any, that ENGINEER has used in
preparing the Bid Documents.
B. Copies of reports and drawings referenced in paragraph 4.03.A will be made
available by OWNER to any Bidder on request. Those reports and drawings are not part of the
Contract Documents, but the “technical data” contained therein upon which Bidder is entitled to
rely as provided in paragraph 4.06 of the General Conditions has been identified and established
in paragraph 4.06 of the Supplementary Conditions. Bidder is responsible for any interpretation
or conclusion Bidder draws from any “technical data” or any other data, interpretations,
opinions, or information contained in such reports or shown or indicated in such drawings.
4.04 Provisions concerning responsibilities for the adequacy of data furnished to prospective
Bidders with respect to subsurface conditions, other physical conditions and Underground
Facilities, and possible changes in the Bidding Documents due to differing or unanticipated
conditions appear in paragraphs 4.02, 4.03, and 4.04 of the General Conditions. Provisions
concerning responsibilities for the adequacy of data furnished to prospective Bidders with
respect to a Hazardous Environmental Condition at the Site, if any, and possible changes in the
Contract Documents due to any Hazardous Environmental Condition uncovered or revealed at
the Site which was not shown or indicated in the Drawings or Specifications or identified in the
Contract Documents to be within the scope of Work appear in paragraph 4.06 of the General
Conditions.
4.05 On request, OWNER will provide Bidder access to the Site to conduct such
examinations, investigations, explorations, tests, and studies as Bidder deems necessary for
submission of a Bid. Bidder shall fill all holes and clean up and restore the Site to its former
Repair & Paint
Countryview & Bluewater Tanks 00100-3 Job No. 41-459
Packet Pg. 135
condition upon completion of such explorations, investigations, tests, and studies.
4.06 Reference is made to Article 7 of the Supplementary Conditions for the identification of
the general nature of other work that is to be performed at the Site by OWNER or others (such as
utilities and other prime contractors) that relates to the Work for which a Bid is to be submitted.
On request, OWNER will provide to each Bidder for examination access to or copies of Contract
Documents (other than portions thereof related to price) for each other work.
4.07 It is the responsibility of each Bidder before submitting a Bid to:
A. examine and carefully study the Bidding Documents, including any Addenda and the
other related data identified in the Bidding Documents;
B. visit the Site and become familiar with and satisfy Bidder as to the general, local, and
Site conditions that may affect cost, progress, and performance of the Work.
C. become familiar with and satisfy Bidder as to all federal, state, and local Laws and
Regulations that may affect cost, progress, or performance of the Work;
D. carefully study all reports of explorations and tests of subsurface conditions at or
contiguous to the Site and all drawings of physical conditions in or relating to existing surface or
subsurface structures at or contiguous to the Site (except Underground Facilities) which have
been identified in the Supplementary Conditions as provided in paragraph 4.02 of the General
Conditions, and carefully study all reports and drawings of a Hazardous Environmental
Condition, if any, at the Site which have been identified in the Supplementary Conditions as
provided in paragraph 4.06 of the General Conditions;
E. obtain and carefully study (or assume responsibility for doing so) all examinations,
investigations, explorations, tests, studies, and data concerning conditions (surface, subsurface,
and Underground Facilities) at or contiguous to the Site which may affect cost, progress, or
performance of the Work or which relate to any aspect of the means, methods, techniques,
sequences, and procedures of construction to be employed by Bidder, including any specific
means, methods, techniques, sequences, and procedures of construction expressly required by
the Bidding Documents, and safety precautions and programs incident thereto;
F. agree at the time of submitting its Bid that no further examinations, investigations,
explorations, tests, studies, or data are necessary for the determination of its Bid for performance
of the Work at the price bid and within the times and in accordance with the other terms and
conditions of the Bidding Documents;
G. become aware of the general nature of the work to be performed by OWNER and
others at the Site that relates to the Work as indicated in the Bidding Documents;
H. correlate the information known to Bidder, information and observations obtained
from visits to the Site, reports and drawings identified in the Bidding Documents, and all
additional examinations, investigations, explorations, tests, studies, and data with the Bidding
Repair & Paint
Countryview & Bluewater Tanks 00100-4 Job No. 41-459
Packet Pg. 136
Documents;
I. promptly give ENGINEER written notice of all conflicts, errors, ambiguities, or
discrepancies that Bidder discovers in the Bidding Documents and confirm that the written
resolution thereof by ENGINEER is acceptable to Bidder; and
J. determine that the Bidding Documents are generally sufficient to indicate and convey
understanding of all terms and conditions for the performance of the Work.
4.08 The submission of a Bid will constitute an incontrovertible representation by Bidder that
Bidder has complied with every requirement of this Article 4, that without exception the Bid is
premised upon performing and furnishing the Work required by the Bidding Documents and
applying any specific means, methods, techniques, sequences, and procedures of construction
that may be shown or indicated or expressly required by the Bidding Documents, that Bidder has
given ENGINEER written notice of all conflicts, errors, ambiguities, and discrepancies that
Bidder has discovered in the Bidding Documents and the written resolutions thereof by
ENGINEER are acceptable to Bidder, and that the Bidding Documents are generally sufficient to
indicate and convey understanding of all terms and conditions for performing and furnishing the
Work.
ARTICLE 5 - SITE AND OTHER AREAS.
5.01 The site is identified in the Bidding Documents. All additional lands and access thereto
required for temporary construction facilities, construction equipment, or storage of materials
and equipment to be incorporated in the Work are to be obtained and paid for by
CONTRACTOR. Easements for permanent structures or permanent changes in existing
facilities are to be obtained and paid for by OWNER unless otherwise provided in the Bidding
Documents.
ARTICLE 6 - INTERPRETATIONS AND ADDENDA.
6.01 All questions about the meaning or intent of the Bidding Documents are to be submitted to
ENGINEER in writing. Interpretations or clarifications considered necessary by ENGINEER in
response to such questions will be issued by Addenda mailed, emailed, faxed or delivered to all
parties recorded by ENGINEER as having received the Bidding Documents. Questions received
less than ten days prior to the date for opening of Bids may not be answered. Only questions
answered by Addenda will be binding. Oral and other interpretations or clarifications will
be without legal effect.
6.02 Addenda may be issued to clarify, correct, or change the Bidding Documents as deemed
advisable by OWNER or ENGINEER.