BOARD OF COUNTY COMMISSIONERS
AGENDA REQUEST
DATE: February 5, 2013
TO: Honorable Chairman and Members of the Board
FROM: Jeff Littrell
SUBJECT: Eglin AFB Utilities Privatization (UP) Proposal
DEPARTMENT: Water and Sewer
BCC DISTRICT: All
STATEMENT OF ISSUE: OCWS is requesting BCC approval to submit a proposal for Eglin
AFB Utilities Privatization (UP) and authorize the Chairman to sign the proposal/contract offer
documents on behalf of Okaloosa County Water & Sewer. Eglin UP is for the potable water
distribution system and the wastewater collection system. Please note that Eglin UP does not
include wastewater treatment & disposal - OCWS has a separate, independent contract for the
treatment & disposal of wastewater from Duke Field, Eglin Main Base, and Camp Rudder. A
PowerPoint file is attached which gives a broad overview of Eglin AFB Utilities Privatization.
BACKGROUND: In accordance with 10 U.S.C. §2688 - Utility Systems: Conveyance
Authority, The Defense Energy Support Center (DESC) and/or Defense Logistics Agency (DLA)
seek to identify and obtain information from responsible sources in connection with the
privatization of the water distribution and wastewater collection systems at Eglin Air Force Base
(AFB), Florida. Privatization is defined as the conveyance of a utility system to a municipal,
private, regional, district, or cooperative utility company or other entity. The conveyance may
consist of all right, title, and interest of the United States in the utility system. The expected term
of a contract is 50-years.
On June 7, 2011, the BCC gave direction to OCWS to pursue the above-mentioned Eglin AFB
Utilities Privatization (UP), where OCWS would serve as the system owner (SO) and we would
assemble a team, composed of a contract operations company and a program
manager/engineering firm. On September 6, 2011, the BCC approved the selection of
Environmental Services Group (ESG) for contract operations and The Constantine Group (TCG)
for program management/engineering. This approval was based on a recommendation from a
selection committee. Since then, OCWS has entered into Master Services Agreements (MSAs)
with ESG and TCG. The purpose of these MSAs is to setup a contract that allows these two
companies to work with OCWS to prepare the Eglin UP proposals after DLA issues the Request
for Proposal (RFP). The proposals are very voluminous and complex - it is a tremendous
amount of work to be done in a relatively short period of time. Four (4) volumes will be required
for the water distribution system, and four (4) volumes will be required for the wastewater
collection system. In addition, two (2) more volumes are required to make a joint proposal for
both water and wastewater. All in all, the total proposal is about 12” thick. The MSAs for ESG
and TCG stipulate that they will prepare the proposals for the County, at no cost to the County.
If the County is successful and is selected for Eglin UP, ESG and TCG will enter into a 5-year
contract with OCWS. There is a great amount of time and risk incurred by ESG and TCG,
because there is the possibility that UP will not be awarded at all, due to the federal budget
situation. It is also possible that the UP may be awarded to some other proposer. If/when the
Eglin UP was to be awarded to the County, then ESG and TCG would still not be compensated
for their work in putting together the proposal. At that time, the County would negotiate rates
with ESG and TCG for a 5-year contract. If the County desires to utilize ESG and/or TCG
beyond the 5-year period, the County has the option of nine 5-year renewals. Again, per the
MSAs, under no scenario will ESG and/or TCG be compensated by the County for their work
preparing the proposals.
On Sept 28, 2012, DLA issued the RFP for privatization of the water distribution system and
wastewater collection system of Eglin AFB. Since then, OCWS, ESG, TCG, and their sub-
consultants - CDM-Smith, HDR, Veterans Consulting & Contracting, and Gustin, Cothern, &
Tucker - have been working diligently on a proposal, which is due to DLA on or before February
19. Of the 10 volumes being submitted, Volume 3 of the water and Volume 3 of the wastewater
serve as the contract documentation. This contract documentation (Volume 3) is attached for
your review. All the other volumes are specific to water and sewer. The infrastructure-related
topics include information such as, but not limited to the following: information about OCWS,
past performance documentation, references, transition plan, emergency response plan, service
interruption plan, catastrophic loss plan, O&M/Quality Management Plan, Initial Systems
Deficiency Corrections (ISDCs) plan, Initial Repair and Replacement (R&R) plan, 50-year CIP
for R&R, and financial information.
Volume 3 was prepared by HDR, who has been successfully awarded prior UP contracts at other
Air Force bases, and input was provided by OCWS, TCG, and other County staff. Volume 3 has
since been through the County Contract Review process and has been revised further with input
from Purchasing, Risk Management, Legal, and Contracts & Grants. Because the legal
documentation was so voluminous, Ms. Heather Encinosa (Nabors, Giblin & Nickerson) assisted
Mr. Dowd with the legal review/input. Like HDR, Ms. Encinosa has prior UP experience at
other Air Force bases. The County Contract Review coordination sheet is also attached for your
review. The OCWS UP Team is now in the process of reviewing and printing the 10 volumes.
OCWS is requesting that the BCC authorize the Chairman to sign the pertinent sections of the
proposal/contract offer, on behalf of OCWS, at the appropriate time before Feb 19. Currently,
there is still a lot of printing, binding, and collating to be done. Should the BCC approve this
agenda item and authorize the Chairman to sign, OCWS would get the final documentation to the
Chairman for signatures during the week of February 11.
After the February 19 submittal, the future timeline is somewhat uncertain. It is possible that the
Federal Government will further delay UP or place it on hold. If DLA does intend to move
forward awarding a contract to OCWS, there would be negotiations and then OCWS would enter
into a contract for a transition period, which is expected to be 6-9 months. During this period,
the infrastructure would transition from being operated and maintained by Eglin to being
operated and maintained by OCWS. During this transition period, OCWS would be taking a full
inventory of the system and doing an investigation/analysis on the infrastructure, mostly
underground. OCWS would be able to opt out of the contract or we would be able to renegotiate
the contract and enter into the final 50-year contract. At the conclusion of the transition period,
OCWS would be given a Bill of Sale, and we would be responsible for owning, operating,
maintaining, and replacing the water distribution system and wastewater collection system for a
period of 50 years. At the end of the 50-year contract, the infrastructure reverts back to Eglin
AFB or there is the possibility to re-negotiate.
If OCWS were to be awarded the contract for Eglin UP, this transaction would yield great
benefits to OCWS rate payers and to Okaloosa County as a whole. As the owner, we would
enhance our existing relationship with Eglin AFB by establishing a 50-year relationship. We
would maintain control of decision making and how to most effectively utilize our resources.
The ownership role provides for a greater opportunity to create new sources of positive cash
flow, which assists in stabilizing operations, and potentially in mitigating future rates increases.
Our expanded operations could also serve to facilitate investigating other consolidation of
services opportunities in the local and regional area.
OPTIONS: Approve or Deny.
RECOMMENDATIONS: Staff recommends BCC approval to submit a proposal for Eglin UP
and to authorize the Chairman to sign the proposal/contract offer documents on behalf of
Okaloosa County Water & Sewer.
RECOMMENDED BY:
APPROVED BY:
James D. Curry, County Administrator