CHANGE ORDER FORM
Date: 14 Aug 2015 confract No.: _C14-2184-FM Change Order No.: _14-08
Owner: __ OKALOOSA COUNTY BOARD OF COUNTY COMMISSIONERS
Coniractor:___ Lord & Son Construction, Inc.
CHANGE YO CONTRACT PRICE
DESCRIPTION - AMOUNT
Original Contract Price: $ 10,000.00
Net change by previously authorized Change Orders; 983,219.87
Present Contract Price: 993,219.87
(14,443.71)
This Change Order will (add/@‘é@
$ 978,776.16
New Contract Price:
CHANGE TO CONTRACTTIME
DESCRIPTION _ - — DATE or NUMBER OF DAYS
Original Contract Time: TBD TBD
Original Substantial Completion Date: IBD
Net change by previously authorized Change Orders: N/A
This Change Order will (add/deduct): N/A
New Contract Time: N/A
New Substantial Completion Date: N/A
APPROVALS
REQUESTED BY: DATE:
PROJECT ENGINEER: DATE:
CONTRACTOR: Levené) ] N la)d DATE:
OWNER;: DATE:
This Change Crder is an amendment to the Contract/Agreement between Contractor and the
Owner, and all other contract provisions shall remain in full force and effect unless specifically
amended in writing, signed by both parties.
§
CHANGE OWNER 0
ORDER ARCHITECT 0
CONTRACTOR 0
FIELD 0O
AIA DOCUMENT G701 (Modified) OTHER 0
PROJECT: New Office Addition at the Okaloosa
County Sheriff's Office in Shalimar CHANGE ORDER NUMBER: Eight (8)-Final
(name, address) 50 2" Street DATE: 14 August 2015
Shalimar, FL 32579
TO CONTRACTOR: ARCHITECT'S PROJECT NO: 14007
(name, address)
Lord & Son Construction, Inc. CONTRACT DATE: May 12, 2014
Post Office Box 1808
Fort Walton Beach, FL 32549 CONTRACT FOR: CM @ Risk Services
The Contract is changed as follows:
Lord & Son is returning, as savings to the Owner, the unused balance for the following Contract Line
ltems:
‘General Requirements $10,830.00
Contingency 3.613.71
Total Savings $14,443.71
Not valid until signed by the Owner and Contractor.
$10,000.00
$983,219.87
The original (Contract SUM) Was.........ccooiiiiiiir i e
?\Jet change by previously authorized Change Orders...........ccoooovciiinninnn,
The {Contract Sum) prior to this Change Orderwas ..........cocccoviiiiiiiiciiiiiees $993,219.87
The (Contract Sum)) will be (decreased) by this Change Order in the amount of ($14,443.71)
The new (Contract Sum) including this Change Orderwillbe ..................ocooiie $978,776.16
The Contract Time will be changed by: N/A
The date of Substantial Completion as of the date of this Change Order therefore is: Per Contract
NOTE: This summary does not reflect changes in the Contract Sum, Contract Time or Guaranteed Maximum Price which have been authorized
by Construction Change Directive.
DAG Architects, Ing. Lord & Son Construction, Inc, Okaloosa County BOCC
T S Conlractor - Qwar '
1223 Airport Road Post Office Box 1808 1804 Lewis Turner Blvd., Ste. 100
Dastin, FL 32541 Fort Walton Beach, FL. 32549 Fort Walton Beach, FL 32647
Addre7 /%/[ /’Z T Address Addrass
By.... f M By, W @ &/f‘g . By,
Chatles W. Clary Ill, FAI Leven D. Lord Nathan D. Boyles
Chief Financial Officer Chairman
Architect
Date: él/ / 46 A ; Date: g/;&f ) Date:
AIA DOCUMENT G701 + CHANGE ORDER » 1887 EDITION < AA + 1987 « THE AMERICAN INSTITUTE OF ARCHITECTS
1755 NEW YORK AVE, NW., WASHINGTON, DC. 20008 G701-1987 (Modified)
Contract No: C14-2184-FM
New Office Addition at the Okaloosa County Sheriff's Office in Shalimar
General Requirements Summary
Beginning General Requirements from GMP $13,779.00
CO2-B Johnny By the Sea - Inv. #13460 $53.00
Johnny By the Sea - Inv. #1346 $53.00
Johnny By the Sea - Inv. #13588 $53.00
Disposal Services - Inv. #138223 $309.00
Johnny By the Sea - Inv. #13755 $53.00
Johnny By the Sea - inv. #13890 $53.00
Disposal Services - Inv. #0000140368 $309.00
Johnny By the Sea - Inv. #14077 $53.00
Disposal Services - Inv. #0000141708 $618.00
Johnny By the Sea - Inv. #14230 $53.00
Disposal Services - Inv. #0000143218 $618.00
Johnny By the Sea - Inv. #14688 $53.00
Disposal Services - inv. #0000144577 $618.00
Johnny By the Sea - Inv. #14825 ©$53.00 :
Ending General Requirements Balance ' $10,830.00
Contract No: C14-2184-FM
New Office Addition at the Okaloosa County Sheriff's Office in Shalimar
Contingency Summary
Beginning Contingency from GMP . ‘ $39,790.00
Co2-X i o .
Kirby - EWO to analyze building to meet 148 MPH wind load $500.00
Henley Concrete & Masonry - Draw #4
CO2-Add curb/remove-pour back pads $3,000.00
Joe Dereuil Associates - Inv. #14174-01
Structural engineering services $262.50
ODP PO 21500369 Smith Ironworks (Partial) $1,913.00
Harrington - Draw #4
Extend conduit $1,418.00
Contingency - Mowrey Elevator - Draw #1
Remanufacture Piston $2,500.00
Contingency - Area Glass - Draw #3
Add glass and glazing ‘ $92.87
Contingency - SCI - Draw #4
Add one week boom-lift rental $953.18
Contingency -Lawrence Commercial - Draw #2
Aluminum Door Canopy $3,700.00
Contingency - H & T - Draw #2 (Balance)
Site revisions $4,805.00
Contingency - Kirby - Inv. #017234
Canopy @ East walk door $968.84
Contingency - Smith lronworks - Inv. #50608
. |Materials for stair rails $2,029.90
Contingency - Smith lronworks - Inv. #50609
Labor for stair rails $3,800.00
Line CO2 - 2 - Bonds, Insurance, Permits
Savings to Contingency ($6,239.35)
Line CO2 - E - Fencing Allowance
Add to fencing allowance $385.00
Line CO2 - J - Millwork
Credit for base cabinet @ 209 Briefing ($1,836.00)
Contingency - Smith Ironworks - 6/25/15
Steel grate at elevator pit $106.00
Contingency - GSC Systems - Draw #3Rev
Additional access control wiring $2,496.00
Contingency - Keller - Draw #6
Add for 1 Hr. Ceiling $628.00
Contingency - Harrison - Draw #3
Fire retardant paint; stairwell floor $825.00
Contingency - Warren HM Doors - Draw #1
Dutch door access control $742.00
Contingency - Southern Plumbing - Draw #3
Reinstall air line $980.00
Contingency - Harrington - Draw #7
Add fir alarm; changes @ F/A, firestop $8,629.00
Contingency - Peaden Prior Month CO4
Billed to Line CO2 - U in error; goes to CO2 - X $1,389.41
Contingency - Savings from pre-engineered bldg. ($285.12)
Contingency - Savings from concrete reinforcement
($2,246.90)
Contingency - Bill Burch Inv. 8171 - Add signs @ Marshall
Inspection $249.10
Contingency - Keller - Draw #8 - Patch wall @ fire riser $175.00
Contingency - Bayside Fire Protection - Draw #6 - Change
FDC @ fire riser ‘ $1,135.00
Contingency - Harrington - Draw #8 - Add exit lights $766.00
Contingency - Peaden - Draw #6 - Exhaust fan @ evidence
room $1,008.94
Contingency - Fail-Safe - Knox Box $196.95
Contingency - Estimated Sales Tax Savings
$1,128.97
Ending Contingency Balance
$3,613.71