Old Antioch Change Order No. 1 from the Okaloosa County BOCC meeting of October 16, 2012 (IQM2 meeting #1099). Original portal label: Old Antioch Change Order No. 1. Preserved as a historical public record; part of the meeting linked as a related source.
- Original publication
- Old Antioch Change Order No. 1
- Date
- October 16, 2012
- Reference collection
- Okaloosa County Board of County Commissioners (IQM2 public portal)
View reference catalogue / source ↗
Download this source
Machine-extracted text — 90-Old Antioch Change Order No. 1.pdf
Text extracted on 2026-10-29 from 90-Old Antioch Change Order No. 1.pdf using optical character recognition (ocrmypdf/tesseract). Not human-corrected; may contain recognition errors. Read alongside the source images.
File · 0.0 MB
Download ↓Old Antioch Change Order No. 1 (PDF)
Original PDF as published on the Okaloosa County IQM2 meeting portal.
PDF · 0.8 MB
Download ↓
Full text
Machine-extracted from the source by optical character recognition. Not yet human-corrected — it may contain recognition errors. Read it alongside the images above.
CHANGE ORDER FORM
Okaloosa County Public Works
CHANGE ORDER NO. 1
DATE: November 8, 2012
PROJECT NAME: Old Antioch Road Improvements
OWNER: OKALOOSA BOARD OF COUNTY COMMISSIONERS
CONTRACTOR: Gum Creek Farms, Inc.
The following changes are hereby made to the CONTRACT DOCUMENTS:
999-025-001 1' of granular material to be added below the 6" granular subbase for drainage
purposes.
999-025-002 Additional time of 10 days to perform additional work
CHANGE TO CONTRACT PRICE: $ 60,450.00
ORIGINAL CONTRACT PRICE: $ 558,968.10
CONTRACT PRICE adjusted by previous Change Order: $ 558,968.10
NEW CONTRACT PRICE including Change Order $ 619,418.10
CHANGE TO CONTRACT TIME: 10 days
APPROVALS:
Requested By: CL 4 4 :
Project Engineer: GILLE va
Ounce goo
(= 7
Contractor: > 2 ww
—_
ONE COMPANY | Many Solutions
November 6, 2012
Jason Autrey
Okaloosa County Engineer
1759 S. Ferdon Blvd.
Crestview, FL 32536
RE: Additional Work at Old Antioch Road
Due to the proximity of the water table to the bottom of the granular subbase on Old Antioch Road it
has been recommended that an additional 12” of existing material be excavated and replaced with a
sand material. This will allow for additional drainage to occur underneath the granular subbase and
Type B 12.5 base material. This will occur from STA 29+00 to STA 46+00 from the left edge of subgrade
to the right ditch, an approximate width of 32’.
The cost for this additional work will come from existing Pay Items and will be as follows:
Pay Item Description Estimated Quantity Unit Price Total Price
120-4 Subsoil Excavation 2015 CY $10.00 $20,150.00
120-6 Embankment 2015 CY $20.00 $40,300.00
Total Additional Cost: $60,450.00
This work will also involve additional time in order to complete the broader scope of work. This
additional time is estimated at 8 days. This time will be added on to the original contract time of 80
days, increasing the contract time to 88 days (not including weather days to date).
Please let me know if you have any questions or concerns.
Sincerely,
—
athan Vannoy
Project Administrator
HDR Construction Control Corporation
Jason Autrey
From: Don Amunds
Sent: Thursday, November 08, 2012 2:36 PM
To: Jim Curry; Jason Autrey; John Hofstad
Cc: Richard Brannon; Jack Allen; John Dowd
Subject: Re: Old Antioch Road Reconstruction
We will do it.
Don R. Amunds
Okaloosa County Commissioner, District 4
850-651-7105
Please note: Due to Florida's very broad public records laws, most written communications to or from County employees
regarding County business are public records, available to the public and media upon request. Therefore, this written e-
mail communication, including your e-mail address, may be subject to public disclosure.
From: Jim Curry
To: Jason Autrey; John Hofstad
Cc: Richard Brannon; Jack Allen; John Dowd; Don Amunds
Sent: Thu Nov 08 14:32:13 2012
Subject: RE: Old Antioch Road Reconstruction
Ok — I’m good with proceeding provided we do an after-the-fact confirmation to the board for the next meeting.
From: Jason Autrey
Sent: Thursday, November 08, 2012 12:30 PM
To: Jim Curry; John Hofstad
Cc: Richard Brannon; Jack Allen
Subject: Old Antioch Road Reconstruction
Jim,
John said he mentioned it to you this morning, but the contractor has encountered an unanticipated subsurface
condition that we need to address immediately. The existing material beneath the lower portion of Old Antioch Road is
not responding well to wet conditions. Based on design borings we anticipated more favorable material, but it turns out
that mixed in with the soils are organics and large tree stumps. In order to allow for the roadway to provide an
adequate service life (20-25 years), the poor material needs to be removed and then replaced with clean sand.
In our construction documents we already have line items that will account for the material we need. However, the
amount in the current bid documents is significantly lower than what will be required to perform the full extent of the
work. In talking with Purchasing, we are required to obtain BCC approval for the significant increase in the line item
quantities. | will prepare the agenda request for presentation on 11/20, however if we wait that long to notify the
1
contractor we will have to contend with additional de-mobilization and site maintenance costs (i.e. claims) due to our
delay. The existing contract is for approximately $560,000, this change is for approximately $60,000.
With your concurrence, | would like to authorize the contractor to execute the work associated with the attached
change order immediately then present the matter to the BCC as an “after the fact” item at the next meeting. In the
long run this will save the county a substantial amount of money by properly installing the work and minimizing delay
costs.
Should you have any question, please feel free to contact me.
Thanks,
Jason
Jason T. Autrey, P.E.
County Engineer - Okaloosa County Public Works
1759 S. Ferdon Blvd - Crestview, FL 32536 - 850-689-5772
aa
ed
dounssy/
Please note: Due to Florida’s very broad public records laws,
most written communications to or from County employees
regarding County business are public records, available to the
public and media upon request. Therefore, this written e-mail
communication, including your email address, may be subject
to public disclosure.